Woodlawn Landfill Gas Power Station Works

BMA Energy was further engaged to carry out the rebuild and major overhaul of Generator #3 at Woodlawn Power Station.

Engine Installed Pic 1

BMA Energy was further engaged to carry out the rebuild and major overhaul of Generator #3 at Woodlawn Power Station. The full project scope included the complete removal of the engine skid package, overhaul of the engine, supply and replacement of the crankshaft and re-installation and commissioning of the rebuilt engine. Our team leveraged their familiarity with the site to deliver another successful work for our client, completing a timely zero hour rebuild of Generator #3, ensuring its continued operation into the future.